2023-24 park, building and road projects

This page shows works projects from a previous financial year. Projects for the current financial year can be found here.

Council completes a wide range of construction projects each year to deliver new and improved services to the community and maintain and renew infrastructure assets. The table below provides project details.

In 2023-24 Council plans to deliver $100.7 million in works. As at 31 May 2024, $74.7 million has been spent.

Council is committed to delivering effective, efficient services that meet the expectations and needs of the community. As part of that commitment, Council is providing information on the capital works program to ensure open and transparent communication with the community.

2023-2024 project information (parks, buildings and roads)

Progress legend

On track – On track
Behind schedule – Behind schedule
On hold – On hold
Rescheduled – Rescheduled
Completed – Completed

Works or engagement notification only – Works or engagement notification only; refer to the relevant program page line for financial information

Black square – Part of the GreenWay project.

Black triangle - Part of the Urban Amenity Improvement Program.

Suburb Location Program Anticipated completion Status Progress  Budgeted 2023/24 ($,000) Full Year Spent 2023/24 ($,000) May-24 Further information
Multiple suburbs Playgrounds Playgrounds renewal and upgrade Aug 2024 Completed Completed
 2,729 664 Playground Program
Multiple suburbs  Multiple Locations Pedestrian safety improvements Jun 2026 Works in progress On track  2,004 1,686 Pedestrian Access and Mobility Plan (PAMP) Program
 Multiple suburbs

Petersham Park 

Colgate Reserve

Footpath Renewal   July 2024 Completed Completed
Works or engagement notification only Works or engagement notification only Footpath Renewal Petersham Park & Colgate Reserve 
Multiple suburbs

 Lewis Herman Reserve

Cahill Street Playground

Bay Run Lighting

 Public Spaces Project  Aug 2023 Completed Completed 170 163 New Public Spaces Project
Ashfield Ashfield Park Sporting Ground Sand Grooving Oct 2024 Commencing On track
- - Sporting Ground Sand Grooving
Ashfield Arthur Street Road Resurfacing Jul 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter  (PDF 161.8KB)
Ashfield Albert Parade Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 183.8KB)
Ashfield Albert Parade Road Resurfacing May 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 183.9KB)
Ashfield  Charlotte Street  Kerb Blister Islands and Kerb Ramps  Nov 2023 Completed Completed Works or engagement notification only Works or engagement notification only

Consultation Letter (PDF 212.2KB)

Consultation Plan (PDF 806.3KB)

Ashfield Clissold Street Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 183.8KB)
Ashfield Clissold Street Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 184KB)
Ashfield Elizabeth Street Footpath Improvements Jul 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only
Road and Footpath Improvements at Elizabeth Street, Ashfield
Ashfield Elizabeth Street at Oak Street Kerb Blister Islands Nov 2023 Completed Completed  Works or engagement notification only Works or engagement notification only

Consultation Letter (PDF 213.8KB)

Consultation Plan (PDF 660.6KB)

Ashfield Hammond Park Amenities Upgrade Jul 2025 Planning On track - Hammond Park Amenities Upgrade
Ashfield Holden Street Kerb Blister Nov 2023 Completed Completed  Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 118KB)
Ashfield Margaret Street Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 161.7KB)
Ashfield Mackay Street Footpath Renewal Oct 2023 Completed Completed   Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 107.4KB)
Ashfield Milton Street Footpath Renewal Feb 2024  Completed Completed  Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 101.2KB)
Ashfield Miller Avenue Road Upgrade  May 2024 Completed Completed
 Works or engagement notification only  Works or engagement notification only

Notification Letter (PDF 130.7KB)

Notification Plan (PDF 6.8MB)

Ashfield Tideswell Street Kerb Extensions and Kerb Ramps Feb 2024 Completed Completed  Works or engagement notification only
Works or engagement notification only

Consultation Letter (PDF 248.6KB)

Consultation Plan  (PDF 553.1KB)

Ashfield Victoria Street In-lane Bus Stop Platform Dec 2023 Completed Completed  Works or engagement notification only Works or engagement notification only Notification Letter (PDF 118.3KB)
Ashfield  Victoria Street  Road Resurfacing  Mar 2024 Completed Completed  Works or engagement notification only Works or engagement notification only Notification Letter  (PDF 183.5KB)
Ashfield

 Yeo Park

Victoria Street

Reconciliation Action Plan Mar 2024 Completed Completed  450 361 Yeo Park Aboriginal Survival Memorial
 Ashfield Yeo Park  Playground Strategy Plan Jun 2024 Completed Completed  35 38 Yeo Park Ashfield
Ashfield Victoria Square Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 183.8KB)
Ashfield Victoria Square Road Resurfacing May 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.9KB)
Annandale Albion Street Road Resurfacing Mar 2024 Completed Completed  Works or engagement notification only Works or engagement notification only
 Notification Letter (PDF 183.8KB)
Annandale Annandale Town Hall and Community Centre Refurbishment Jun 2025 Planning Completed
 20 -  Annandale Town Hall and Community Centre
Annandale Bayview Lane Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 183.7KB)
Annandale Collins Street Footpath Renewal Sep 2023 Completed Completed  Works or engagement notification only Works or engagement notification only Notification Letter  (PDF 248KB)
Annandale Pritchard Street Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 183.9KB)
Annandale Pritchard Street Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 184.1KB)
Annandale Regent Street Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only  Notification Letter (PDF 183.9KB)
Annandale Regent Street  Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 184KB)
Annandale Tebbutt Street Footpath Renewal Apr 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Consultation Letter (PDF 267.7KB)
Balmain Balmain Town Hall

Ground floor  - library upgrade and building renewal works

Aug 2024 Completed Completed
 3,788 2,708 Balmain Town Hall upgrade project
Balmain Beattie Street Pedestrian Crossing Upgrade  Apr 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter  (PDF 117.5KB)
Balmain Clayton Street Footpath Renewal Sep 2023 Completed
Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 240.6KB)
Balmain

Dawn Fraser Baths - Elkington Park

Access improvements -Northern pavilion refurbishment

Sep 2026
Planning On track
 135 196 Dawn Fraser Baths project
Balmain Darling Street and Elliott Street Main Street Improvement Works  Sep 2023 Completed Completed  Works or engagement notification only  Works or engagement notification only

Consultation Letter (PDF 289.9KB)

Consultation Plan (PDF 1.2MB)

Balmain Darling Street Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.9KB)
Balmain Elliott Street Intersection upgrade Oct 2023 Completed Completed  Works or engagement notification only Works or engagement notification only

Notification Letter (PDF 151.1KB)

Notification Plan (PDF 509.9KB)

Balmain Gladstone Park New Public Toilets  Jun 2025 Planning On track   20  2

Gladstone Pk Amenities project

Balmain Isabella Street Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Balmain Llewellyn Street Stormwater Improvements April 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only

Notification Letter (PDF 161.2KB)

Notification Plan  (PDF 2.3MB)

Balmain Paringa Reserve

Demolition of former Pelegrinis Restaurant. Construction of new kiosk and public toilet

Sep 2024 Completed Completed
280 198 Elliot Street Kiosk project
Balmain  Unnamed Lane  Road Resurfacing  Mar 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter  (PDF 183.6KB)
Balmain Vincent Street Improving Stormwater Drainage Feb 2024 Completed Completed Works or engagement notification only Works or engagement notification only

Consultation Letter  (PDF 242.2KB)

Consultation Plan  (PDF 532.6KB)

Birchgrove Birchgrove Park

Sport field fencing

- Completed Completed  3 3

 Birchgrove Park project 

Birchgrove Birchgrove Park Amenities Upgrade and renewal   Jun 2026  Planning On track  20 2 Birchgrove Park Amenities project
 Birchgrove Ferdinand Street Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.6KB)
 Birchgrove Gow Street   Kerb Extension  Feb 2024 Completed Completed Works or engagement notification only Works or engagement notification only

Notification Letter  (PDF 402.9KB)

Notification Plan (PDF 2.6MB) 

Birchgrove Grove Street Road Resurfacing Mar 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter  (PDF 195.2KB)
Birchgrove Numa Street Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Birchgrove The Terrace Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Birchgrove The Terrace  Kerb Extension Nov 2023 Completed Completed Works or engagement notification only
Works or engagement notification only

Notification Letter (PDF 405.4KB)

Notification Plan (PDF 1.2MB)

Birchgrove  Water Street Road Resurfacing  Mar 2024 Completed Completed
Works or engagement notification only Works or engagement notification only
Notification Letter  (PDF 195.2KB)
Camperdown Denison Street Proposed Kerb Blister and Kerb Ramp Feb 2024 Completed Completed Works or engagement notification only
Works or engagement notification only

Consultation Letter (PDF 222.8KB)

Consultation Map  (PDF 519.3KB)

Camperdown Derby Place Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 492.7KB)
Camperdown Pyrmont Bridge Road

PRUAIP-New cycleway

Parramatta Rd to Mallet St

Aug 2025 Concept Design On hold  Black triangle Black triangle  Camperdown Cycle Way project
Croydon Centenary Park Sporting Ground Sand Grooving Oct 2024 Commencing On track
- - Sporting Grounds - Sand Grooving
Dulwich Hill Bedford Crescent Traffic Facilities Upgrade Aug 2024 Completed Completed
Works or engagement notification only Works or engagement notification only

Notification Letter (PDF 127.6KB)

Notification Plan (PDF 3.3MB)

Dulwich Hill Canonbury Grove Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 184KB)
Dulwich Hill Canonbury Grove Road Resurfacing May 2024 Completed Completed
Works or engagement notification only Works or engagement notification only Notification Letter (PDF 184.1KB)
Dulwich Hill Challis Avenue Stormwater Drainage Upgrade Oct 2023 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 118KB)
Dulwich Hill

Dulwich Hill Station Precinct

Wardell Road

Dudley Street

Ewart Street

Improvement to cycleway

Various traffic management

Public domain

Jun 2024 Completed Completed
1,000  585 Dulwich Hill Station Precinct  project
 Dulwich Hill Fairfowl Street Streetscape Improvements May 2024 Completed Completed
Works or engagement notification only Works or engagement notification only Notification Letter (PDF 129.1KB)
Dulwich Hill Hoskins Park

Park Upgrade

Jan 2025

Procurement

and Design

On track 42  9 Hoskins Park project
Dulwich Hill Johnson Park Park Masterplan upgrades Feb 2025 Design On track  Black square   Black square  Johnson Park Upgrade project
Dulwich Hill Kintore Street Road Resurfacing Aug 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 183.8KB)
Dulwich Hill Kintore Street Road Resurfacing Jun 2024 Completed Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 184.1KB)
Dulwich Hill Loftus Street Road Resurfacing  Mar 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only
Notification Letter (PDF 195.1KB)
Dulwich Hill, Lewisham, Summer Hill, Leichhardt

GreenWay
In-corridor works between Taverners Hill and Dulwich Hill

Path, lighting, landscape and art works

Apr 2025 Procurement Behind schedule  Black square   Black square  GreenWay website
GreenWay Your Say Inner West
Dulwich Hill Wardell Road Footpath Renewal Apr 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only Consultation Letter (PDF 267KB)
Enmore Cavendish Street Road Resurfacing May 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Enmore Edgeware Road Traffic Signal Upgrade Jun 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only 

Notification Letter (PDF 145.3KB)

Notification Plan (PDF 1.9MB)

Haberfield Algie Park Sporting Ground Sand Grooving Oct 2024 Commencing On track
- - Sporting Grounds - Sand Grooving
Haberfield Dudley Street (1-3) Stormwater Drainage Improvements  Oct 2023 Completed Completed  Works or engagement notification only Works or engagement notification only

Consultation Letter (PDF 199.6KB)

Consultation Plan (PDF 333.9KB)

Haberfield Dudley Street (50-52) Stormwater Drainage Improvements  Oct 2023 Completed Completed Works or engagement notification only
Works or engagement notification only

Consultation Letter (PDF 197.8KB)

Consultation Plan (PDF 288.2KB)

Haberfield  Percy Street Road Resurfacing Mar 2024 Completed Completed Works or engagement notification only Works or engagement notification only
Notification Letter  (PDF 183.7KB)
Haberfield Ramsay Street Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Haberfield Rawson Street Stormwater Drainage Upgrade  May 2024 Completed Completed
Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 117.2KB)
Haberfield Turner Avenue Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Leichhardt Allen Street Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 182KB)
Leichhardt Blackmore Oval Pedestrian Bridge Replacement Jun 2024 Completed Completed  -  -

Notification Letter (PDF 486.3KB)

Detour Map (PDF 209.3KB)

Leichhardt Edith Street Footpath Renewal   Feb 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter (PDF 107.3KB)
Leichhardt Flood Street Footpath Renewal Aug 2023 Completed Completed Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 254.9KB)
Leichhardt Flood Street Footpath Renewal  Mar 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter (PDF 107.5KB)
Leichhardt Hill Street Footpath Renewal Aug 2023 Completed  Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 248.2KB)
Leichhardt John Street Footpath Renewal Aug 2023 Completed Completed Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 240.5KB)
Leichhardt  Macaulay Street Footpath Renewal Mar 2024 Completed Completed
Works or engagement notification only Works or engagement notification only Notification Letter  (PDF 134.9KB)
Leichhardt McDonald Street Footpath Renewal Nov 2023 Completed Completed  Works or engagement notification only Works or engagement notification only
Notification Letter (PDF 253.4KB)
Leichhardt Parramatta Road Various upgrades Jun 2024 Completed Completed
 Works or engagement notification only Works or engagement notification only  Parramatta Road Urban Renewal
Leichhardt

Leichhardt Park Aquatic (LPAC)

Mary Street

Aquatic centre upgrade Dec 2025 Design On track 880 1,022 Leichhardt Park Aquatic project
Leichhardt Pioneer Memorial Park New Public Toilets Dec 2023 Completed Completed 860 852 Pioneer Park New Public Toilets  
Leichhardt Styles Street Footpath Renewal Feb 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 252.6KB)
Lewisham Toothill Street Footpath Renewal Jul 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 101.1KB)
Lilyfield  Alberto Street Kerb Blister Islands and Kerb Ramps Mar 2024 Completed Completed Works or engagement notification only
Works or engagement notification only

Consultation Letter  (PDF 226.1KB)

Consultation Plan (PDF 619.6KB)

Lilyfield

Leichhardt Oval No2

Glover Street

Amenities Upgrade Oct 2024 Commencing On track
- - Leichhardt Oval No.2 New Amenities
Lilyfield

Leichhardt Oval No2

Waterfront Drive

Embankment extension and Sporting Ground Sand Grooving Oct 2024 Commencing On track
- - Sporting Grounds - Sand Grooving
 Lilyfield

Callan Park

Waterfront Drive

Callan Park Tidal Baths  Jan 2026  Consultation On track  -  Callan Park Tidal Baths
Lilyfield O'Neill Street  Stormwater Drainage Upgrade Feb 2024 Completed Completed 670 665

Notification Letter (PDF 1.4MB)

Notification Plan (PDF 1.2MB)

Lilyfield, Rozelle
The Bay Run
Lighting upgrade through Leichhardt Park and King George Park Aug 2023 Completed
Completed
 Black square Black square  New public spaces projects
Marrickville

Annette Kellerman

Aquatic Centre

Aquatic Centre Upgrade  Sep 2024 Completed Completed
1,750 1,234 Annette Kellerman Aquatics Project
Marrickville Beaman Park Bridge Retrofitting of stairs Jun 2024 Completed Completed Works or engagement notification only
Notification Letter (PDF 455.9KB)
 Marrickville Carrington Road Cycleway Upgrade Apr 2024 Completed Completed
Works or engagement notification only  Works or engagement notification only 

Notification Letter (PDF 133.1KB)

Notification Plan (PDF 17.6MB)

Marrickville

Henson Park

Centennial Street

Henson Park Grandstand Redevelopment Jun 2025 Commenced On track  - - Henson Park Grandstand Redevelopment
Marrickville Chalder Street Footpath Renewal Sep 2023 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 247.5KB)
Marrickville Grove Street Road Resurfacing  Jun 2024 Completed Completed  Works or engagement notification only Works or engagement notification only Notification Letter (PDF 161.9KB)
Marrickville

Henson Park

Centennial Street

 Henson Park Upgrade May 2024 Completed Completed
 660 566 Henson Park Upgrade Works
Marrickville

HJ Mahoney

Memorial Reserve

Sporting Ground and Amenities Upgrade Mar 2024 Completed Completed 2,300 2,120 HJ Mahoney Memorial Reserve Sporting Ground and Amenities Upgrade
Marrickville Kings Lane Road Resurfacing Mar 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 195.2KB)
Marrickville Mackey Park Mackey Park Upgrade Feb 2025 Commencing On track

  Mackey Park Upgrade
Marrickville Mackey Park

Park Masterplan Upgrade

Canoe Ramp

Aug 2024 Completed Completed
500 13 Mackey Park Canoe Ramp Upgrade
Marrickville Mackey Park Amenities Upgrade  Mar 2025 Planning On track  - - Mackey Park Amenities Upgrade
Marrickville

Marrickville Town Hall

St Peters Town Hall

Town Hall Upgrades Aug 2023 Completed Completed 100 66 Marrickville/ St Peters Town Hall External Upgrade
Marrickville

Marrickville Park

Fraser Street

 Marrickville Park Dog Off Leash Fencing May 2024 Completed Completed  70 8 Marrickville Park Dog Off Leash Fencing
Marrickville Murray Street Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.6KB)
Marrickville Petersham Road Stormwater Drainage Upgrade Nov 2023 Completed Completed Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 229.3KB)
Marrickville Marrickville Park  Cricket Net Upgrade Sep 2023 Completed Completed  - - Marrickville Park Cricket Net Upgrade
Marrickville Murray Street Road Resurfacing  Apr 2024 Completed Completed Works or engagement notification only Works or engagement notification only
Notification Letter  (PDF 184KB)
Marrickville Rich Street Road Resurfacing  Jul 2024 Completed Completed
Works or engagement notification only Works or engagement notification only Notification Letter (PDF 270.7KB)
Marrickville Tuohy Lane Road Resurfacing  Mar 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter  (PDF 195KB)
Marrickville

Victoria Road

at Meeks Road

Traffic Facilities Jul 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only

Notification Letter (PDF 122.1KB)

Notification Plan (PDF 3.2MB)

Marrickville Wardell Road Footpath Renewal Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter (PDF 101KB)
Newtown Baltic Street Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 184.1KB)
Newtown Baltic Street Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 184.2KB)
Newtown Chelmsford Street Footpath Renewal  Sep 2023 Completed Completed Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.9KB)
Newtown Commodore Street Footpath Renewal Sep 2023 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 240.8KB)
Newtown Darley Street Footpath Renewal  Oct 2023 Completed Completed  Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 248.4KB)
Newtown Ferndale Street Footpath Renewal Sep 2023 Completed Completed Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.5KB)
Newtown Holt Street Footpath Renewal Sep 2023 Completed Completed Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 240KB)
Newtown

King Street

at Goddard Street

Traffic Facilities Jul 2024 Completed Completed
Works or engagement notification only Works or engagement notification only 

Notification Letter (PDF 122.1KB)

Notification Plan (PDF 3MB)

Newtown  Laura Street Pedestrian Crossing  Sep 2023 Completed Completed Works or engagement notification only
Works or engagement notification only

Consultation Letter (PDF 216.2KB)

Consultation Plan (PDF 778.1KB)

Newtown

Newtown Town Hall

 

Town Hall compliance and upgrade works in coordination with proposed Pride Centre

Jul 2024 Completed Completed
2,725 1,862 Newtown Town Hall Pride Centre Refurbishment
Newtown Oxford Street Footpath Renewal Sep 2023 Completed Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 240.1KB)
Newtown Peace Reserve Park Upgrade Oct 2024 Commencing On track
- -

Notification Letter (PDF 132.8KB)

Notification Plan (PDF 2MB)

Newtown Rawson Street Footpath Renewal Sep 2023 Completed Completed Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.7KB)
Newtown Wells Street Footpath Renewal Apr 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 107.8KB)
Newtown Wells Street Pedestrian Safety Oct 2023 Completed Completed Works or engagement notification only  Works or engagement notification only 

Consultation Letter (PDF 191.1KB)

Consultation Plan (PDF 736.8KB)

Petersham Addison Road Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter (PDF 181.7KB)
Petersham

Albert Street and

James Street Intersection

 Traffic Facilities Aug 2023 Completed Completed Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 122.7KB)
Petersham

Bright Street, Middle Street,

and North Street intersection

Traffic Facilities Aug 2023 Completed Completed  Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 123.1KB)
Petersham

KU Petersham

Preschool

Structural rectification

building condition works

Dec 2025 Planning On track 45 30 Children's Services Work Program
Petersham Margaret Street Footpath Renewal May 2024 Completed Completed Works or engagement notification only Works or engagement notification only Notification Letter   (PDF 101.1KB)          
Petersham McRae Street  Road Resurfacing Jul 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 287.5KB)
Petersham

Park Street

Station Street

Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 183.7KB)
Petersham

Park Street 

Station Street

Road Resurfacing May 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.8KB)
Petersham Petersham Town Hall

Masterplan upgrade

 compliance works

Dec 2023 Completed Completed
400 370 Petersham Town Hall project
 Petersham Petersham Town Hall

 Petersham Town Hall

Roof Remediation Works

 May 2024 Completed Completed
 - - Petersham Town Hall Upgrade Works
Petersham Railway Street Road Resurfacing  Jul 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 259.4KB)
Petersham West Street Traffic Facilities  Jan 2024 Completed Completed Works or engagement notification only Works or engagement notification only 

Notification Letter (PDF 122.4KB)

Notification Plan (PDF 4.6MB)

Rozelle Callan Street Road Resurfacing Apr 2024 Completed Completed
Works or engagement notification only Works or engagement notification only
Notification Letter (PDF 183.9KB)
Rozelle Cross Street Road Resurfacing Jun 2024 Completed Completed
Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.8KB)
Rozelle Evans Street Footpath Renewal Apr 2024 Completed Completed Works or engagement notification only Works or engagement notification only
Consultation Letter (PDF 265.1KB)
Rozelle Evans Street Road Resurfacing Jun 2024 Completed Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.8KB)
Rozelle King George Park Amenities Upgrade Sep 2024 Completed Completed
 - - King George Park Amenities Upgrade
Rozelle  Manning Street Road Resurfacing Apr 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter  (PDF 184KB)
Rozelle Mansfield Street Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Rozelle Napoleon Street Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 183.7KB)
Rozelle Toelle Street  Road Resurfacing Apr 2024 Completed Completed Works or engagement notification only
Works or engagement notification only
Notification Letter  (PDF 184KB)
Summer Hill Edward Street Kerb Blister Islands Nov 2023 Completed Completed Works or engagement notification only Works or engagement notification only

Notification Letter (PDF 126.1KB)

Notification Plan (PDF 3.2MB)

Summer Hill  Grosvenor Crescent  Proposed Raised Thresholds (Speed Humps) Feb 2024 Completed Completed
Works or engagement notification only Works or engagement notification only

Consultation Letter (PDF 210.6KB)

Consultation Plan  (PDF 1.2MB)

 Summer Hill Hardie Avenue Raised Pedestrian Crossing  Apr 2024 Completed Completed  Works or engagement notification only Works or engagement notification only

Notification Letter (PDF 402.3KB)

Notification Plan (PDF 3.2MB)

Summer Hill Sloane Street Traffic Facilities Feb 2024 Completed  Completed Works or engagement notification only
Works or engagement notification only

Notification Letter  (PDF 143.7KB)

Notification Plan  (PDF 7.6MB)

 Summer Hill Smith Street Streetscape Improvement Works  Aug 2023 Completed Completed 382 382

Consultation (PDF 122.9KB)

Consultation Plan (PDF 9.9MB)

Summer Hill Summer Hill Sustainability Hub  Solar Panel Installation Apr 2024 Completed Completed - - Summer Hill Sustainability Hub
Stanmore Cavendish Street Road Resurfacing Aug 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 183.5KB)
Stanmore Cavendish Street Traffic Facilities Jan 2024 Completed Completed  Works or engagement notification only Works or engagement notification only

Notification Letter (PDF 122.2KB)

Notification Plan (PDF 7.3MB)

Stanmore Northumberland Avenue Footpath Renewal  Sep 2023 Completed Completed Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 248.1KB)
Stanmore Sebastopol Street Footpath Renewal   Oct 2023 Completed Completed  Works or engagement notification only
Works or engagement notification only
Notification Letter (PDF 107.3KB)
Stanmore Trafalgar Street Speed Hump Upgrade Jun 2024 Completed Completed  Works or engagement notification only Works or engagement notification only 

Notification Letter (PDF 139.6KB)

Notification Plan (PDF 2MB)

St Peters Canal Rd/Princess Hwy/Mary St Cycleway construction Aug 2023 Completed Completed 50  8 WCX M5 - Canal Rd/Princes Hwy/Mary St Cycleway
St Peters

Camdenville Park

May Street

Camdenville Park upgrade Mar 2025 Works in progress  On track 1,650 327  Camdenville Park Upgrade
 St Peters Camdenville Park Amenities Refurbishment Mar 2025 Planning On track 20 3 Camdenville Park Amenities Refurbishment
 St Peters May Street Road Resurfacing May 2024 Completed Completed  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 181.7KB)
 St Peters Talbot Street Road Resurfacing Jul 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 236KB)
Sydenham Northcote Street and Sydenham Road Pedestrian and Stormwater Improvements Feb 2024 Completed Completed  Works or engagement notification only Works or engagement notification only
 Notification Letter (PDF 126.7KB)
Sydenham Sydenham Station Cycleway construction Jun 2024 Completed Completed
    Sydenham Station Cycleway
Sydenham

Burrows Avenue 

George Street

WestConnex M5 - St Peters Interchange Active Transport Works - Sydenham Station Cycleway  Jun 2025 Design Behind schedule   -  - WestConnex M5 - St Peters Interchange Active Transport Works - Sydenham Station Cycleway
Tempe Barden Street Road Resurfacing Jun 2024 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 161.9KB)
Tempe

Robyn Webster Building

Tempe Reserve

Refurbishment of indoor sporting facility Sep 2023 Completed Completed 500 427 Robyn Webster Building  
Tempe Griffiths Street Road Resurfacing Jul 2024 Completed Completed
Works or engagement notification only
Works or engagement notification only Notification Letter (PDF 161.7KB)
 Tempe Griffiths Street Footpath Renewal Aug 2023 Completed Completed Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 240.1KB)
Tempe Henry Street Road Resurfacing Jun 2024 Completed Completed  Works or engagement notification only  Works or engagement notification only Notification Letter (PDF 161.8KB)
Tempe

Tempe Reserve

Holbeach Avenue

Natural sportsfield drainage upgrade Mar 2024 Completed Completed 1,115 1,015 Tempe Reserve Natural Sports Fields Drainage Upgrade 
 Various Urban Amenity Improvement Program
      50 (17)  
 Various GreenWay Program         13,869 10,733  
 Various Roads
      12,656 5,800  
 Various Kerb & Gutter Renewal

      1,140 133  
 Various Roadside Furniture

       - -  
 Various Footpaths         4,884 3,791  
 Various Traffic Facilities
        2,096 1,008  
 Various Stormwater         2,247 1,569  
Various  Car Parks         - 9  
 Various Bridges
        449 267  
 Various Cycleways
        229 48  
 Various Town Centres
        1,024 670  
 Various Sporting Ground Upgrades
        2,275 1,497  
 Various Parks Plans of Management and Masterplan          467 286  
 Various Park Assets Renewal and Minor Works         1,632 1,101  
 Various Wharves         134 121  
 Various Early Learning Centre
        127 56  
 Various Community Buildings & Libraries
        856 406  
 Various Property Buildings
        1,000 457  
 Various Aquatic Centres 
        160 382  
 Various Park Buildings 
        589 303  
 Various  Sea Walls         50 21  
 Various Callan Park Swim Site         80 10  
 Various Community Wellbeing and Culture
        271 37  
 Various Fleet
        6,785 6,388  
 Various Property & Assets
        19,685 19,281  
 Various ICT
        378 279  
 Various Resource Recovery         2,500 2,513  

Open the link below to see the projects and works completed by Council in the previous financial year:

Projects from 2022-23

Rate this page

  • Rate as The content was useful18.75% The content was useful votes
  • Rate as The content was not useful81.25% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 17 Sep 2024