Annette Kellerman Aquatic Centre Upgrade
Project address: Annette Kellerman Aquatic Centre, Black Street, Marrickville
Project description: This project is to replace end of life plant at the aquatic centre and improve sustainability and energy performance. Planned works include:
Stage 1:
- Replacement of aluminium composite cladding on roof structure.
Stage 2:
- Replacement of heating and cooling plant with fully electrified heat pump and chiller system.
- Expand existing solar panels.
- Roof louver and skylight replacement.
Progress: Stage 1 works are completed and stage 2 works are in the planning phase.
Expected timeframes:
- Stage 1: January 2024-October 2024
- Stage 2: April 2028- September 2028
Budget: Stage 1: $2M
Contact: Alex Nord on 02 9335 2191 or alex.nord@innerwest.nsw.gov.au
Detailed Progress Update November 2023 (PDF 310.1KB)
Detailed Progress Update June 2023 (PDF 299.4KB)
Stage 1 Completed Photos