Missing links – Davis Street tunnelling works

What are we doing in this area?

The upgrades in the area from Waratah Mills light rail station to Johnson Park include:

  • A new tunnel under Davis Street, Dulwich Hill
  • A boardwalk from the Davis Street tunnel to Johnson Park along the light rail corridor
  • Installation of new solar smart path lights
  • Public art in tunnel
  • Wayfinding signage
  • Upgrade of drainage at Terry Road

The construction method for the new pedestrian and cycling tunnel under Davis Street is a ‘top-down’ construction method, that requires specialised equipment and includes about 85 piles. The piling is complete, the concrete has been poured for the tunnel roof, the waterproofing is installed, the asphalt has been put in place, the line marking completed, and the bridge re-opened on 17 October, approximately six months after closure. The tunnel is excavated from underneath. This is the fastest method to build the tunnel and ensured the shortest closure of Davis Street bridge.

When are we doing this?

Construction of the upgrade from Waratah Mills light rail station to Johnson Park has started in April 2024 and is anticipated to be completed in 2025.

Davis Street bridge has re-opened

Davis Street bridge in Dulwich Hill is open again, after just over 6 months of closure for tunnelling works for a new GreenWay shared path connection.

Images

Artist impression - Dulwich Hill: view towards tunnel under Davis Street, from the south looking north:

Dulwich Hill view towards tunnel from south of Davis Street

The construction method for the new pedestrian and cycling tunnel under Davis Street is a ‘top-down’ construction method, that requires specialised equipment and includes about 85 piles. The piling is complete, the concrete has been poured for the tunnel roof, the waterproofing is installed, the asphalt has been put in place, the line marking completed, and the bridge re-opened on 17October, approximately six months after closure. The tunnel is excavated from underneath.

First tunnel breakthrough on 20 September 2024:

Davis St tunnel breakthrough

Continued tunnel works (10 December 2024):

Davis St tunnel 10 Dec 2024

Elevated shared path footings from Johnson Park to Terry Road in Dulwich Hill:

Path JP to Terry Rd 10 Dec 2024

 Line markings added and Davis Street bridge reopened (17 October 2024):

Davis St bridge line marking 17 Oct 2024

Asphalt is completed on the Davis Street bridge (3 October 2024):

Davis St bridge asphalt 2 - Oct 2024

Concrete pour for kerbs and footpath on the Davis Street bridge (25 September 2024):

Davis Street bridge concrete pour for kerbs and footpath 25 Sep 2024

Sub-road surface being installed on the Davis Street bridge (16 September 2024):

Davis St bridge sub layer

Waterproofing (10 September 2024):

Davis St bridge waterproofing 2

Davis St bridge waterproofing detail

Concrete tunnel roof has been poured and is curing (15 August 2024):

Davis St concrete pour complete 2

Getting ready for concrete pour (5 August 2024):

Davis St tunnel ready for concrete pour of ceiling

Preparation works for path construction:

 Davis St path prep - 3 July 2024

explore content banner

GreenWay construction updates

Works in progress

Upcoming works

Completed works

 

Rate this page

  • Rate as The content was useful100.00% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 17 Dec 2024