Missing links – Davis Street tunnelling works

What are we doing in this area?

The upgrades in the area from Waratah Mills light rail station to Johnson Park include:

  • A new tunnel under Davis Street, Dulwich Hill
  • A boardwalk from the Davis Street tunnel to Johnson Park along the light rail corridor
  • Installation of new solar smart path lights
  • Public art in tunnel
  • Wayfinding signage
  • Upgrade of drainage at Terry Road

The construction method for the new pedestrian and cycling tunnel under Davis Street is a ‘top-down’ construction method, that requires specialised equipment and includes about 85 piles. Once the piling is complete, the concrete will be poured for the tunnel roof, the road surface can be reinstalled, and the bridge re-opened. Then the tunnel will be excavated from underneath. This is the fastest method to build the tunnel and ensures the shortest closure of Davis Street bridge. The tunnel piling works are scheduled to commence Friday 19 April and expected to take approximately two months.

When are we doing this?

Construction of the upgrade from Waratah Mills light rail station to Johnson Park has started in April 2024 and is anticipated to be completed in 2025.

Closure of Davis Street bridge

In order to complete these upgrades, Davis Street bridge is scheduled to be closed for six months until September 2024. Traffic management and detours are in place.

Images

Artist impression - Dulwich Hill: view towards tunnel under Davis Street, from the south looking north:

Dulwich Hill view towards tunnel from south of Davis Street

The construction method for the new pedestrian and cycling tunnel under Davis Street is a ‘top-down’ construction method, that requires specialised equipment and includes about 85 piles. Once the piling is complete, the concrete can be poured for the tunnel roof, the road surface can be reinstalled, and the bridge re-opened. Then the tunnel will be excavated from underneath. Piling works on Davis Street bridge:

Davis St bridge piling full rig

Davis St bridge piling in action - 8 May 2024

Davis St piling rig 2B

Construction site fencing and compound have been installed after the closure of Davis Street bridge: 

Davis St piling rig

explore content banner

GreenWay construction updates

Works in progress

Upcoming works

Completed works

 

Rate this page

  • Rate as The content was useful100.00% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 02 Jul 2024