PRUAIP-Dot Lane Cycleway

The Parramatta Road Urban Amenity Improvement Program  (PRUAIP)- Leichhardt

PRUAIP Objective

The project seeks to improve the environmental qualities of the inner west and see the importance of achieving sustainability outcomes within the projects.  The projects shall contribute to overall biodiversity outcomes, reduction of urban heat island, increased urban forest cover, improved air and water quality and other environmental opportunities that the project can provide.

The PRUAIP is a NSW State Government, $198 million initiative under the Parramatta Road Corridor Urban Transformation Program. The Parramatta Road corridor and the UAIP extend from Granville to Camperdown, and include projects in Granville, Auburn, Homebush, Burwood, Kings Bay, Taverners Hill, Leichhardt and Camperdown. The vision for the Corridor, developed by Urban Growth NSW, is for a high-quality multi-use corridor with improved transport choices, better amenity and balanced growth of housing and jobs.

The project seeks to improve the environmental qualities of the inner west and see the importance of achieving sustainability outcomes within the projects.  The projects shall contribute to overall biodiversity outcomes, reduction of urban heat island, increased urban forest cover, improved air and water quality and other environmental opportunities that the project can provide.

The aim of the PRUAIP is to reverse the urban decay and lack of design cohesion along Parramatta Road.  The NSW State Government believes the PRUAIP will deliver tangible public benefits contributing to the delivery of liveable communities and neighbourhoods. The public domain upgrades along the corridor are envisaged to help to rectify the market failure and stimulate new development.

Design & construction of a new cycleway at Dot Lane, Leichhardt, linking Hay St to Norton St and Renwick Lane

  • Project address:   Dot Lane/ Hay Street, Leichhardt
  • As part of the overall improvement to connectivity a new East west cycleway connection is proposed along Dot Lane between Norton Street, Balmain Road and through to Hay Street through the existing surface carpark.

A temporary link between Balmain Road and Renwick Lane (a shared path along Parramatta Rd) is included and will be delivered as part of the PRUAIP package

This will improve connectivity and will assist with the future activation of the existing lanes and existing hostile carpark areas.

Opportunities for tree planting to provide shade and assist with wayfinding will also be explored

Other works include:

-Cycling facilities

- Underground electricity

- New Multifunction Poles & lights

-Road Safety Improvements to Hay Street

   
  • Progress: 
  • Works are complete

Underground electrical works are complete

- The  project was delayed due to the COVID shutdown

- Ausgrid outage and removal of overheads is complete. Street lights are complete.

- Hay Street raised pedestrian crossing is complete

- New stormwater drainage system complete

- Easement thru the back of the Crow Bar is complete

-Footpath works for Hay St to Parramatta Rd is complete

  • Project completed: July 2022
  • Contact:

 

  • Progress Photos

Dot Lane Photo Sep 22

Dot Lane finished 1

Dot Lane finished 2

  • Pre Works Photo

Dot Ln Carpark 20190405_094835

Dot Ln Carpark 20190405_094835

 

 
  • In Progress Photos

Dot Lane Progress  

  • Design Plan

Dot Lane Plan

Dot Lane Plan 2

  

Rate this page

  • Rate as The content was useful100.00% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 12 Sep 2023