Tempe Reserve Pedestrian Lighting Upgrade Project address: Tempe Reserve, Holbeach Ave, Tempe Project description: Upgrade of pedestrian pathway lighting with additional lights to new LED fittings. Progress: Construction contract awarded Demolition in completed and Poles and wiring have been removed Foundation for new poles is under construction Expected completion date: April 2023 Budget: $1,200,000 Contact: Bill Pearce (02) 9392 5445, bill.pearce@innerwest.nsw.gov.au