Ashfield Aquatic Centre Sun shade Improvements

Extra Shade Improvements 

Project Address: Ashfield Aquatic Centre, 160 Elizabeth Street, Ashfield

Project Description:  Planned Sun Protection works in 2 stages.

Stage 1:

  • Installation of shade cloth to fencing to shield leisure pool - completed
  • Installation of shade cloth to fencing to shield creche - completed
  • Installation of shade sail to creche garden - completed
  • Install shade sail to timber seats near 50m and program pools – completed
  • Extend shade sail fitted to existing grandstand structure - completed

Stage 2: 

  • Relocation of 6 umbrellas from grandstand and 1 from leisure pool – completed
  • Erection of temporary shade structure to grandstand – completed
  • Removal of temporary shade structure – completed
  • Erection of 2 permanent steel structures and shade to grandstand and leisure pool – June 2023

Expected completion date: July 2023

Progress: 

  • Stage 1 completed
  • Stage 2 : Scheduled to be completed July 2023

Contact: Alex Nord on (02) 9335 2191 or alex.nord@innerwest.nsw.gov.au

 

Rate this page

  • Rate as The content was useful33.33% The content was useful votes
  • Rate as The content was not useful66.67% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 03 May 2023