Lewisham to Newtown cycle link
Project description:
The Regional Route 7 cycleway upgrades are being delivered in 2 sections:
Stage 1 : Trafalgar Street between Railway Terrace and Abels Lan -Petersham
Construction of Kerb & Gutter and Footpath with signs and line markings. This included TfNSW final approval of four traffic signals design across the route.
Stage 2 : Petersham Station to Newtown
Completion Dates:
- Section 1 completed December 2021.
- Section 2 completed: June 2022.
Contact for further information:
- Dany Estephan from Ally Civil on 0416 294 702 or destephan@allycivil.com.au
- Snezana Bakovic, Inner West Council on 9335 2228 or snezana.bakovic@innerwest.nsw.gov.au
Responding to your feedback:
Community feedback has shaped every stage of the design of the cycleway. In response to community feedback, Inner West Council has cancelled the proposed tree removal in Section 2 The post construction review will be organised after each project stage completion. Residents’ concerns raised during construction will be taken in consideration.
Read more about the project and community engagement on the cycleway design at the Your Say Inner West website