This project is an annual program of park footpath renewal to improved footpath condition and safety. This year’s program comprised works in the following parks. Surrounding residents and park users were notified of the works prior to commencement in each park.

Outstanding work has been deferred to the 22/23 program.

Suburb Park Address  Works  Progress
Ashfield Ashfield Park Parramatta Road & Orpington Street  Concrete path repair with concrete and filter paving 70% complete the remainder deferred to 22/23 Fin Year.
Ashfield Yeo Park 296A Old Canterbury Road Concrete path repair with concrete and filter paving Completed
Balmain Ann Cashman Reserve Elliott Street Relaying pavers and replacing pavers with filter paving Completed
Balmain Birrung Park Donnelly Street Relaying pavers and replacing pavers with filter paving Completed
Balmain Colgate Park Colgate Avenue Decomposed granite replacement Deferred to 22/23 Fin Year.
Balmain Gladstone Park Darling Street & Darvall Street  Concrete path repair with  concrete, asphalt and filter paving Deferred to 22/23 Fin Year.
Balmain Punch Park Wortley Street Concrete Path repairs Completed
Birchgrove Ballast Point Reserve Ballast Point Road Stair Repairs Completed
Birchgrove Birchgrove Park  Rose Street Gravel path repairs, filter pave tree root protection Completed
Birchgrove Birchgrove Park Driveway to Sydney Water Pump Station Access to Snails Bay Completed 
Birchgrove Cove Street Reserve 55 Cove Street Concrete path repair with concreate and filter paving.

Completed

Haberfield Algie Park 195 Ramsay Street Concrete Path repairs concrete and filter paving Completed
Haberfield Robson Park Mortley Avenue & Boomerang Street Concrete path repair with concrete and filter paving

Completed

Leichhardt Pioneer Memorial Park Norton Street Concrete path

 40% complete remainder deferred to 22/23

Leichhardt War Memorial Park 39 Moore Street Concrete path repair with concrete and filter paving Works Commencing
Marrickville Day Street Reserve Day Street Concrete path repair with concrete and filter paving

Deferred to 22/23 Fin Year.

Marrickville McNeilly Park Jersey Street Concrete path repair with concrete and filter paving
Completed
Newtown Camperdown Memorial Rest Park Federation Road, Lennox and Church Street Concrete path repair with concrete Deferred to 22/23 Fin Year.
Petersham Petersham Park West Street & Brighton Street Concrete path repair with concrete and filter paving
10% completed, remainder deferred to 22/23 Fin Year.
Stanmore Maundrell Park Stanmore Road Concrete path repair with concrete Completed
Tempe  Kendrick Park Cnr of Princes Highway & View Street Concrete path repair with concrete and filter paving Deferred to 22/23 Fin Year.
  • Progress: Contract awarded and works scheduled to commence in November 2021
  • Expected completion date:  30 June  2023
  • Budget: Adjusted scope near completion.  Spent $670,000 to 30/6/22.
  • Budget:  for 22-23  $0.77M
  • Contact:  Bill Pearce, Parks Project Manager – 0417 401 083 bill.pearce@innerwest.nsw.gov.au

Rate this page

  • Rate as The content was useful100.00% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 19 May 2023